Stations, vehicles, depots, control centers and corridors installed by one team to one documented standard.
TAP installs complete ITS systems across stations and stops, bus fleets, depots, control centers and the corridors that connect them. Our teams deliver the pathways, power connections, mounting, structured cabling, fiber optic backbone, earthing and configuration that turn delivered equipment into a working system.
Every installation follows approved drawings and method statements, is carried out under an environmental, health and safety management plan, and is tested on completion, with records for each site handed over as as-built documentation.
Installation Scope
Multiple Environments, One Installation Team
Each part of a transit network brings its own conditions, constraints and standards. TAP plans and delivers installation in all five.
Stations & Stops
Installation, local configuration and network configuration of all station equipment, with conduits from the data cabin, power from distribution boards, and every component designed and installed to resist vandalism.
- Fare gates, validators and vending machines
- Passenger displays and IP speakers
- CCTV cameras and help points
- Station data cabin and racks
- Conduits, cable trays and enclosures
- Station Wi-Fi and access switches
- Earthing to every enclosure and rack
- Station drawings, elevations and wiring diagrams
Vehicles
Vehicle preparation, installation, integration and testing of all on-board ITS components, at the vehicle manufacturer's plant or a designated depot, with each installation proven functional on completion.
- AVL units and driver terminals
- On-board validators
- Interior and exterior displays
- On-board cameras and recorders
- Passenger counters
- Communication gateways and antennas
- Wiring harnesses and power connections
- Vehicle-type installation drawings
Control Center
Installation and configuration of all central computer systems, racks and control room equipment, with local cabling to the network and power demarcation points and cutover planned outside operating hours.
- Server racks and central systems
- Video wall and operator consoles
- Operator workstations
- Call center positions
- Equipment room cabling
- UPS and power distribution
- Room layout drawings and elevations
- Off-hours cutover
Depots
Installation of depot systems for vehicle identification, access control, parking and maintenance operations, coordinated with depot activity so fleet operations continue throughout.
- RFID readers and depot gates
- Biometric access stations
- Barriers and entry/exit terminals
- ANPR and occupancy sensors
- Depot LAN and UTP cabling
- Wireless offload points
- Depot servers
- Energy meters and enclosures
Corridor Network
The armored fiber optic backbone in a ring design, with splicing, termination and certification of every segment, together with the corridor wireless network that keeps buses connected.
- Route survey and pathway planning
- Duct installation and cable pulling
- Fiber splicing and termination panels
- Outdoor distribution boxes
- OTDR and loss testing
- Corridor Wi-Fi mesh nodes
- Microwave links where required
- Fiber route documentation
Site Rollout
A Repeatable Sequence at Every Site
Every station, depot and control room is installed to the same sequence, with a generic plan for all sites and documented variations where a site differs.
- Step 01
Site Survey
Conditions, power, pathways and access confirmed on site.
- Step 02
Installation Drawings
Site drawings, elevations and wiring diagrams approved.
- Step 03
Pathways & Power
Conduits, trays, enclosures and power connections prepared.
- Step 04
Mounting & Cabling
Equipment mounted and structured cabling installed.
- Step 05
Termination & Labeling
Connections terminated, cables labeled at both ends, earthing bonded.
- Step 06
Configuration
Local and network configuration of every device.
- Step 07
Installation Test
Functional test on completion and site records issued.
Vehicle Fit-Out
Fleet Installation Without Disrupting Service
TAP installs on-board systems directly or supports the vehicle manufacturer’s own installers with a complete fit-out package, and certifies every vehicle in either case.
The Fit-Out Package
Issued for each vehicle type and configuration- 01Power requirements
- 02Design and installation plans
- 03Fabrication plans
- 04Wiring diagrams and connection instructions
- 05Bills of materials
- 06Commissioning and test instructions
Fit-Out Rules
Applied to every vehicle in the fleet- 01Identical installation per vehicle type and model
- 02Removable through the doors without disassembly
- 03Cables labeled at both ends
- 04Finished to match the bus interior
- 05No hazard to drivers or passengers
- 06Functional test on completion of each vehicle
Workmanship Standards
Installed to Recognized Practice
TAP’s installation teams work to internationally recognized cabling, labeling and earthing practice, so every site is consistent, safe and maintainable.
Structured Cabling
Gigabit copper cabling with Power over Ethernet for cameras, speakers and phones, installed and tested per link.
ISO/IEC 11801 · TIA-568Fiber Optics
Armored high-core-count fiber, fusion spliced and terminated, with every segment tested and certified.
OTDR · Insertion lossLabeling
Cables, ports and equipment identified to a consistent scheme, with cables labeled at both ends.
TIA-606Earthing & Bonding
All enclosures, racks and equipment bonded to a common earthing system, supplemented where site provision is insufficient.
TIA-607Electrical Works
Power from distribution boards with protection, isolation and compliance with local electrical regulations.
Local codesMounting & Fixings
Approved brackets with stainless steel or non-corrosive fixings, tamper-resistant where accessible to the public.
Anti-vandal
Environment, Health & Safety
Safe Sites, Every Shift
All works are delivered under an environmental, health and safety management plan, supervised by dedicated EHS personnel and binding on every subcontractor.
EHS Management Plan
Site risks, controls and responsibilities defined before mobilization.
Method Statements
Approved procedures and risk assessments for each type of work.
Permit to Work
Controlled authorization for electrical, height and roadside work.
Code of Conduct
Binding conduct standards, including gender awareness, for all personnel.
Toolbox Talks
Daily briefings on the hazards of each task and site.
Protective Equipment
Task-appropriate PPE issued, worn and inspected.
Traffic Management
Safe work zones for roadside and corridor installation.
Environmental Controls
Waste, dust and noise managed, with packaging removed and recycled.
Site Records
A Complete Record for Every Site
Each installed site is handed over with a documented record, forming part of the as-built documentation used for testing, maintenance and future expansion.
- 01Site survey reportBefore works
- 02Approved installation drawingsBefore works
- 03Elevations and wiring diagramsBefore works
- 04Method statements and risk assessmentsBefore works
- 05Installation checklistsDuring works
- 06Cabling and fiber test reportsOn completion
- 07Equipment register with serial numbersOn completion
- 08Configuration recordsOn completion
- 09Installation test resultsOn completion
- 10As-built drawingsHandover